1 Project & Pile Information
CMR number from wire delivery sheet.
CMR
Enter your CMR number above
Auto-filled from database — can be changed.
2 Pile Geometry
Drilled / nominal pile diameter (not the cage).
mm
Outside-to-outside of the reinforcing cage — must be less than Pile Dia.
mm
Total length of reinforcing cage.
m
3 Nodes Above Concrete
💡 Known after concreting only. Enter nodes visible above concrete surface per wire.
↑ Enter CMR ID to load wire details.
4 Nodes Folded Up From Bottom
💡 Were any nodes folded up at the end of the wires? Only required if a cage was shortened or an extra cage was not installed after wire installation.
Enter 0 if none were folded.
5 Reference Levels (RL) — All in metres AHD
💡 RL = Reduced Level — Australian Height Datum in metres. TOC can be above, equal to, or below PPL.
Ground or working platform from which the rig drilled.
m RL
Actual RL of concrete top. If above PPL, Formatube assumed.
m RL
Pile head trim RL — usually top ring of cage. Below TOC.
m RL
RL at the very bottom of the drilled hole — below PPL.
m RL
Measured distance from the Cut-Off Level down to the top ring of the reinforcing cage.
mm
🧱 Formatube assumed: TOC is above PPL — a Formatube casing above ground is shown on the diagram.
Water Table Present
— tick if groundwater is encountered
Approximate RL — must be between BOS and PPL.
m RL
Casing Used
— tick if temporary and/or permanent casing was installed
Permanent casing: enter the internal diameter (ID). Temporary casing: enter the outer diameter (OD).
6 Concrete & Volume
Total m³ — include shaft + any above-ground extension (PDA ext., casing above PPL, etc.).
m³
Specified strength class, e.g. 32 MPa, 40 MPa.
Retarders, accelerators or fibres affect the heat signature.
SCM replacement % if known — affects hydration temperature curve.
7 Site & Soil Conditions
Brief description of soil layers with approximate RL boundaries.
8 Additional Notes
Ready to Submit
Click below to save your data to CMR Tech and download an Excel copy to your local folder.
✅ Details Submitted & DownloadedYour data has been saved to CMR Tech's system and an Excel copy has been downloaded to your local folder.
CMR Tech will be in touch shortly regarding your TIP analysis.
CMR Tech will be in touch shortly regarding your TIP analysis.
📐 Pile Parameter Reference Diagram
PPL — Piling Platform Level
TOC — Top of Concrete
COL — Cut-Off Level
BOS/TOE — Bottom of Shaft
Pile Ø — Pile Diameter (mm)
Cage Ø — Cage Diameter (mm)
Formatube Casing (above PPL)
Permanent Casing (C1, C2...)
Temporary Casing
WT — Water Table